The 2021-built 174,000-cbm, Isabella, was on Friday located in the North Atlantic Ocean, offshore Bahamas, after picking up a cargo at the Plaquemines LNG facility earlier this week, its AIS ...
In May 2022, Venture Global took a final investment decision on the first phase of the Plaquemines project with a capacity of 13.3 mtpa and the related pipeline. It also secured $13.2 billion in project financing.
In March last year, the company sanctioned the second phase of the Plaquemines LNG export plant in Louisiana and also secured $7.8 billion in project financing.
The full project, including the second stage, will have a capacity of 20 mtpa coming from 36 modular units, configured in 18 blocks.
Each train has a capacity of 0.626 mtpa.